SEARS资调查与改善计划(WRIP)(三)

Notes, for completing the WRIP Spreadsheet:LL8兆毅咨询
填写WRIP改善计划表的注意事项LL8兆毅咨询

1) Whenever practical, data provided should begin with the recent 2 months prior to the last audit by Sears Holdings Corporation, or begin with the recent 6 months if your factory has not been audited by Sears Holdings Corporation. If factory previously did not have a complete working hour’s information, factory should try the best effort to estimate historical working hours based on previous actual factory practice.LL8兆毅咨询

Sears Holdings Corporation公司曾经审核过的工厂,其提供的资料,应从上一次审核前两个月开始;若是未经Sears Holdings Corporation审核过的工厂,其提供的资料应从最近六个月开始。 如工厂以往没有完整的工作时间记录, 则按过往实际工作时间估计。LL8兆毅咨询

2) Please carry out a thorough monthly analysis of wages and working hours covering all production workers (including those new, trainee, apprentice and slow workers in different departments) in the factory. In order to demonstrate the actual WRIP implementation process at factory level, factory is required to submit the above thorough monthly analysis of wages and working hours covering all production workers on a monthly basis to Sears Holdings Corporation, either by adopting the attached sample document (Appendix B) or by using factory's own equivalent analysis document with format to our satisfaction.LL8兆毅咨询

工厂应全面分析所有生产工人(各部门新进人员,培训人员,学徒工及生手)的工资/工时系统,且用所附表格(附件B)或工厂自己所采用的等同分析表格,对每月的工资/工时原始数据进行分析,并将分析表格按月呈交Sears Holdings Corporation公司。LL8兆毅咨询

3) All data must be true, complete and realistic.LL8兆毅咨询

所有资料数据应真实,完整并且可行。LL8兆毅咨询

4) For section Al: please find out or project the highest accumulated working hours (normal+overtime) of a worker in each month.LL8兆毅咨询

A1项注释,找出并注明工人每月最高工作时间(正常 加班)。LL8兆毅咨询

5) For section A2: please find out or project the lowest rest days of a worker in each month.LL8兆毅咨询

A2项注释:找出并注明工人每月最少休息天数。LL8兆毅咨询

6) For section B 1:please provide the local legal minimum hourly wage for our reference.LL8兆毅咨询

B1项注释:法定当地最低小时工资标准,以供参考。LL8兆毅咨询

7) For section 132: B2项注释: LL8兆毅咨询

a) Please provide the actual and the projected guaranteed minimum hourly wage over a continuous period of 12 months. 列出12个月的实际最低小时工资,或者最低之承诺小时工资。LL8兆毅咨询

b) This hourly wage of a worker can be calculated by "Total monthly gross wage (before reasonable deduction)/ Total monthly working hours (normal+overtime hours) in a month. “Reasonable deduction” includes food, dormitory, water and electricity; but all these deduction items must be properly documented and verifiable by auditor.LL8兆毅咨询

参考工人小时工资计算方法:小时工资=“应发总工资(含合理扣款项)”除以“总工时”。所有类似伙食费,住宿费,水电费等合理工资扣项,必须准确记录,以便评审员可以查核。LL8兆毅咨询

c) Please finds out or project the lowest paid one ("the worst case").LL8兆毅咨询

每月工资总表中,找出实际的最低小时工资水平(最低工查个案)LL8兆毅咨询

d) The projected guaranteed minimum wage must be in a progressively increasing trend, and a fluctuation of up and down in guaranteed minimum wage is not allowed.LL8兆毅咨询

工厂须确保承诺之最低工资标准保持持续改善,不断增长的态势,不得有任何上下波动与偏差。LL8兆毅咨询

8) For section B3:on every month basis. Please provide the actual lowest minimum hourly wage paid to worker (not later than the 30th of the next following month feedback to us) so that we together can continuously identify any gap between the actual paid minimum wage and your guaranteed minimum wage to worker.LL8兆毅咨询

B3项注释:工厂必须提供每月实际发放给工人的最低小时工资金额(此项资料工厂必须在下月30号或之前传给我司),我司将按月审阅实际支付工人的最低工资与工厂承诺支付工人的最低工资是否有差距。LL8兆毅咨询

9) For section C:LL8兆毅咨询

a) Please provide the local legal overtime wage rate (x 1.5,x 2, x 3) for our reference.LL8兆毅咨询
b) For overtime pay to worker, your guaranteed overtime pay should be equal or above the guaranteed minimum hourly wage as mentioned in above 7b.LL8兆毅咨询

C项注释:LL8兆毅咨询

a) 法定当地加班小时工资标准,供参考(1.5倍,2.0倍,3.0倍)LL8兆毅咨询
b) 工厂承诺支付工人的加班工资必须是达到或者高于7b部分所承诺的最低小时工资LL8兆毅咨询